This project combined box culvert construction with solar street lighting foundation works across four towns on the Nansana–Busunju corridor. SSL constructed triple cell box culverts and delivered 249 individual solar light foundations across Nansana, Wakiso, Kakiri, and Busunju.
Box Culvert Works
- Triple cell box culvert construction
- Rock filling: 1,136 M³
- Formwork: 1,546 M²
- Reinforcement: 88 Tonnes
- Concrete: 621 M³
- Waterproofing membrane: 982 M²
Solar Street Light Foundations
- 249 solar light foundation locations
- Locations: Nansana, Wakiso, Kakiri & Busunju towns
Photo Gallery
📷Nansana–Busunju Corridor
Photos Coming Soon
📷Triple Cell Box Culvert
📷Solar Foundation Works
📷Waterproofing Application